Project Implementation Timeline
Milestones Achieved & Projected Targets
| Milestone |
Date Completed / Projected |
| • Property re-zoned to commercial status |
September 2001 |
| • Freedom Park bid process |
March 2005 - December 2005 |
| • MOU signed with Kitwe City Council (KCC) |
12 January 2006 |
| • PGE granted title to property |
September 2006 |
| • Final Addendum to MOU negotiated with KCC |
February 2007 |
| • Environmental Impact Assessment (EIA) process |
November 2006 - February 2008 |
| • EIA Scoping Meeting |
22 May 2007 |
| • EIA Final Submission |
February 2008 |
| • Final formal EIA approval from the Environment Council of Zambia |
17 July 2008 |
| • Investment License granted by the Zambia Development Agency |
November 200 |
| • Approval from equity partner (ZSIPTF) |
November 2009 |
| • Initial disbursement from ZSIPTF |
December 2009 |
| • Began Shopping Mall Construction |
December 2009 |
| • Secured US$10 million dollar facility with BBZ |
December 2010 |
| • Secured private funding to continue works |
April 2012 |
| • Targeted completion & opening for trading |
|